{"id":224,"date":"2022-03-25T18:07:34","date_gmt":"2022-03-25T18:07:34","guid":{"rendered":"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/chapter\/7-6-microsoft-project-tutorial\/"},"modified":"2024-12-28T20:19:55","modified_gmt":"2024-12-28T20:19:55","slug":"7-6-microsoft-project-tutorial","status":"publish","type":"chapter","link":"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/chapter\/7-6-microsoft-project-tutorial\/","title":{"rendered":"7.6 Microsoft Project Tutorial"},"content":{"raw":"The exercise in Table 7.6.1 has the same activities, durations, and predecessors as the exercise we used to develop a network diagram. In this exercise, we have added different dependencies (not only F-S), lags (a positive number showing a delay), and leads (a negative number showing an earlier start).\r\n<table class=\"grid aligncenter\" style=\"height: 324px;width: 870px\"><caption>Table 7.6.1: Activities<\/caption>\r\n<tbody>\r\n<tr style=\"height: 18px\">\r\n<td class=\"shaded\" style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\"><strong>Activity<\/strong><\/td>\r\n<td class=\"shaded\" style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\"><strong>Duration (week)<\/strong><\/td>\r\n<td class=\"shaded\" style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\"><strong>Dependencies<\/strong><\/td>\r\n<td class=\"shaded\" style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\"><strong>Lag<\/strong><\/td>\r\n<td class=\"shaded\" style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\"><strong>Predecessors<\/strong><\/td>\r\n<\/tr>\r\n<tr style=\"height: 18px\">\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">A<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">1<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-S<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">0<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">-<\/td>\r\n<\/tr>\r\n<tr style=\"height: 18px\">\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">B<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">2<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-S<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">0<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">-<\/td>\r\n<\/tr>\r\n<tr style=\"height: 18px\">\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">C<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">2<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-S<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">0<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">A<\/td>\r\n<\/tr>\r\n<tr style=\"height: 18px\">\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">D<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">4<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">S-S<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">0<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">A<\/td>\r\n<\/tr>\r\n<tr style=\"height: 18px\">\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">E<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">1<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-S<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">0<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">B<\/td>\r\n<\/tr>\r\n<tr style=\"height: 18px\">\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">F<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">2<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-S<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">0<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">C, D<\/td>\r\n<\/tr>\r\n<tr style=\"height: 18px\">\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">G<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">3<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-S<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">0<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">E<\/td>\r\n<\/tr>\r\n<tr style=\"height: 18px\">\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">H<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">1<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-S<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">2 weeks<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">G<\/td>\r\n<\/tr>\r\n<tr style=\"height: 18px\">\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">I<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">4<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-S<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">0<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">G<\/td>\r\n<\/tr>\r\n<tr style=\"height: 18px\">\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">J<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">1<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-F<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">-1 week<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">F<\/td>\r\n<\/tr>\r\n<tr style=\"height: 50px\">\r\n<td style=\"text-align: center;vertical-align: middle;height: 50px;width: 84.2656px\">K<\/td>\r\n<td style=\"height: 50px;width: 159.5px;text-align: center;vertical-align: middle\">3<\/td>\r\n<td style=\"height: 50px;width: 177.547px\">\r\n<p class=\"indent\">\u00a0 \u00a0 \u00a0 \u00a0F-S for H<\/p>\r\n<p class=\"indent\">\u00a0 \u00a0 \u00a0 \u00a0S-F for J<\/p>\r\n<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 50px;width: 185.562px\">5 days for J<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 50px;width: 181.656px\">J, H<\/td>\r\n<\/tr>\r\n<tr style=\"height: 17px\">\r\n<td style=\"text-align: center;vertical-align: middle;height: 17px;width: 84.2656px\">L<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 17px;width: 159.5px\">4<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 17px;width: 177.547px\">F-S<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 17px;width: 185.562px\">0<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 17px;width: 181.656px\">I<\/td>\r\n<\/tr>\r\n<tr style=\"height: 59px\">\r\n<td style=\"text-align: center;vertical-align: middle;height: 59px;width: 84.2656px\">M<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 59px;width: 159.5px\">1<\/td>\r\n<td style=\"height: 59px;width: 177.547px\">\r\n<p class=\"indent\">\u00a0 \u00a0 \u00a0 \u00a0F-S for K<\/p>\r\n<p class=\"indent\">\u00a0 \u00a0 \u00a0 \u00a0F-F for L<\/p>\r\n<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 59px;width: 185.562px\">1 week for L<\/td>\r\n<td style=\"text-align: center;vertical-align: middle;height: 59px;width: 181.656px\">K, L<\/td>\r\n<\/tr>\r\n<\/tbody>\r\n<\/table>\r\n<p style=\"text-align: left\">When we start a new project on Microsoft Project, checking \u201cProject Summary Task\u201d under the \u201cFormat\u201d tab is useful. MS Project gives the row number zero to the project summary task. The question mark at the end of the duration shows that the duration is estimated (Figure 7.6.1).<\/p>\r\n\r\n\r\n[caption id=\"attachment_223\" align=\"aligncenter\" width=\"624\"]<img src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2022\/03\/Figure-7.20.jpg\" alt=\"Project Summary Task row on Microsoft Project\" width=\"624\" height=\"59\" class=\"wp-image-210 size-full\" \/> <strong>Figure 7.6.1: Project Summary Task<\/strong>[\/caption]\r\n\r\nBesides, just in the very beginning, it is of high importance to check \u201cCritical Tasks\u201d and \u201cSlack\u201d under the \u201cFormat\u201d tab (Figure 7.6.2). When we type the tasks (activities), the Gantt Chart will highlight the critical tasks in red and the non-critical tasks in blue.\r\n\r\n[caption id=\"attachment_223\" align=\"aligncenter\" width=\"594\"]<img src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.21.jpg\" alt=\"Critical tasks and slack options are checked on Microsoft Project\" width=\"594\" height=\"144\" class=\"wp-image-211 size-full\" \/> <strong>Figure 7.6.2: Checked critical tasks and slack under the Format tab<\/strong>[\/caption]\r\n\r\nAs the durations are in weeks, we should change the settings in the Options under the \u201cFile\u201d tab. \u201cDuration is entered in\u201d is changed to \u201cWeeks\u201d (Figure 7.6.3).\r\n\r\n[caption id=\"attachment_223\" align=\"aligncenter\" width=\"626\"]<img src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.22.jpg\" alt=\"Changing the duration unit in Project Options box on Microsoft Project\" width=\"626\" height=\"260\" class=\"wp-image-212 size-full\" \/> <strong>Figure 7.6.3: Changing the duration unit<\/strong>[\/caption]\r\n\r\nFirst, we should type each activity in the \u201cTask Name\u201d column and durations in the \u201cDuration\u201d column. Then, we can select the predecessors from the dropdown menu in the \u201cPredecessors\u201d column (Figure 7.6.4).\r\n\r\n[caption id=\"attachment_223\" align=\"aligncenter\" width=\"468\"]<img src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.23.jpg\" alt=\"Selecting predecessor A by clicking on A on the dropdown menu\" width=\"468\" height=\"342\" class=\"wp-image-213 size-full\" \/> <strong>Figure 7.6.4: Selecting predecessors from the dropdown menu<\/strong>[\/caption]\r\n\r\nWhen we finish typing all the activity predecessors, the Gantt Chart will be completed on the right side of the window (Figure 7.6.5). As indicated above, red bars show critical tasks (with zero slack) and non-critical tasks (with slacks). MS Project allows the users to change the colors of the bars.\r\n\r\n[caption id=\"attachment_223\" align=\"aligncenter\" width=\"626\"]<img src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.24.jpg\" alt=\"Gantt chart with red bars showing critical tasks (with zero slack) and non-critical tasks (with slacks).\" width=\"626\" height=\"161\" class=\"wp-image-214 size-full\" \/> <strong>Figure 7.6.5: Gantt Chart<\/strong>[\/caption]\r\n\r\nFor this exercise, we are not changing the \u201cTask Mode,\u201d which is either automatically scheduled or manually scheduled (Figure 7.6.6). Project summary tasks are automatically scheduled since they adjust the duration and start and finish dates automatically when activity durations and predecessors are typed.\r\n\r\n[caption id=\"attachment_223\" align=\"aligncenter\" width=\"226\"]<img src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.25.jpg\" alt=\"Task mode dropdown menu showing Manually Scheduled and Auto Scheduled on Microsoft Project\" width=\"226\" height=\"253\" class=\"wp-image-215 size-full\" \/> <strong>Figure 7.6.6: Task mode<\/strong>[\/caption]\r\n\r\nWhen we double-click a task, the \u201cTask Information\u201d window opens (Figure 7.6.7). The dependency type is \u201cFinish-to-Start (FS)\u201d as default. Now we can change dependencies as indicated in Table 7.6.1.\r\n\r\n[caption id=\"attachment_223\" align=\"aligncenter\" width=\"975\"]<img src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.26.jpg\" alt=\"Predecessor tab on task information window. The columns are ID, Task Name, Type, and Lag.\" width=\"975\" height=\"367\" class=\"wp-image-216 size-full\" \/> <strong>Figure 7.6.7: Task Information window<\/strong>[\/caption]\r\n\r\nWhen we are done with predecessor types (dependencies), the predecessors with dependencies different from FS will appear in the \u201cPredecessors\u201d column for the relevant activities (Figure 7.6.8). These dependencies are shown inside a red circle in Figure 7.6.8.\r\n\r\n[caption id=\"attachment_223\" align=\"aligncenter\" width=\"863\"]<img src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.27.jpg\" alt=\"Predecessors and their dependencies on the Predecessors column on Microsoft Project\" width=\"863\" height=\"502\" class=\"wp-image-217 size-full\" \/> <strong>Figure 7.6.8: Predecessors and dependencies<\/strong>[\/caption]\r\n\r\nAfter we change the dependencies, clicking \u201cRespect Links\u201d under the \u201cTask\u201d tab is important since the task mode is manually scheduled, and the new dependencies may affect the precedence relationships. As shown in Figure 7.6.9, MS Project highlights the boxes in light blue if there is a change.\r\n\r\n[caption id=\"attachment_223\" align=\"aligncenter\" width=\"349\"]<img src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.28.jpg\" alt=\"Microsoft Project highlights the changes in a light blue color.\" width=\"349\" height=\"260\" class=\"wp-image-218 size-full\" \/> <strong>Figure 7.6.9: Highlighted changes<\/strong>[\/caption]\r\n\r\nAs shown in Figure 7.6.10, the dependency between A and D is not FS. It is Start-to-Start (SS). Therefore, the arrow starts from the left side of A\u2019s bar on the Gantt Chart and connects to the left side of D\u2019s bar. When it is FS, the arrow starts from the right side of the predecessor and connects to the left side of the successor, as can be seen in Figure 7.6.10 between A and C.\r\n\r\n&nbsp;\r\n\r\n[caption id=\"attachment_223\" align=\"aligncenter\" width=\"523\"]<img src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.29.jpg\" alt=\"Start-to-Start dependency between two activities\" width=\"523\" height=\"294\" class=\"wp-image-219 size-full\" \/> <strong>Figure 7.6.10: Start-to-Start dependency<\/strong>[\/caption]\r\n\r\nTo see the slacks for each activity, we can add a new column named \u201cFree Slack\u201d (Figure 7.6.11). The black underline attached to the left of Activity C in the Gantt Chart also shows the slack (Figure 7.6.10).\r\n\r\n[caption id=\"attachment_223\" align=\"aligncenter\" width=\"371\"]<img src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.30.jpg\" alt=\"Free slack column on Microsoft Project\" width=\"371\" height=\"249\" class=\"wp-image-220 size-full\" \/> <strong>Figure 7.6.11: Free Slack column<\/strong>[\/caption]\r\n\r\nNow we can create an activity network diagram by selecting \u201cNetwork Diagram\u201d on the dropdown menu that appears when we click the Gantt Chart located on the far-left part of the \u201cTask\u201d tab (Figure 7.6.12).\r\n\r\n[caption id=\"attachment_223\" align=\"aligncenter\" width=\"222\"]<img src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.31.jpg\" alt=\"Selecting network diagram from the dropdown menu under Gantt Chart icon\" width=\"222\" height=\"271\" class=\"wp-image-221 size-full\" \/> <strong>Figure 7.6.12: Selecting network diagram<\/strong>[\/caption]\r\n\r\nFigure 7.6.13 displays the network diagram in a non-collapsed format. We should scroll toward the right to see other activities.\r\n\r\n[caption id=\"attachment_223\" align=\"aligncenter\" width=\"624\"]<img src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.32.jpg\" alt=\"Network diagram when it is not collapsed\" width=\"624\" height=\"144\" class=\"wp-image-222 size-full\" \/> <strong>Figure 7.6.13: Network Diagram (Not collapsed)<\/strong>[\/caption]\r\n\r\nTo see the whole diagram without details, we should click \u201cCollapse Boxes\u201d and check \u201cStraight Links\u201d under the \u201cNetwork Diagram Tools \u2013 Format\u201d tab (Figure 7.6.14). The network diagram in MS Project illustrates the links in FS dependency. Therefore, seeing other dependencies on the Gantt Chart view is convenient.\r\n\r\n[caption id=\"attachment_223\" align=\"aligncenter\" width=\"467\"]<img src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.33.jpg\" alt=\"Network diagram when all the labels on the nodes are removed.\" width=\"467\" height=\"219\" class=\"wp-image-223 size-full\" \/> <strong>Figure 7.6.14: Network diagram (Collapsed)<\/strong>[\/caption]","rendered":"<p>The exercise in Table 7.6.1 has the same activities, durations, and predecessors as the exercise we used to develop a network diagram. In this exercise, we have added different dependencies (not only F-S), lags (a positive number showing a delay), and leads (a negative number showing an earlier start).<\/p>\n<table class=\"grid aligncenter\" style=\"height: 324px;width: 870px\">\n<caption>Table 7.6.1: Activities<\/caption>\n<tbody>\n<tr style=\"height: 18px\">\n<td class=\"shaded\" style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\"><strong>Activity<\/strong><\/td>\n<td class=\"shaded\" style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\"><strong>Duration (week)<\/strong><\/td>\n<td class=\"shaded\" style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\"><strong>Dependencies<\/strong><\/td>\n<td class=\"shaded\" style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\"><strong>Lag<\/strong><\/td>\n<td class=\"shaded\" style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\"><strong>Predecessors<\/strong><\/td>\n<\/tr>\n<tr style=\"height: 18px\">\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">A<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">1<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-S<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">0<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">&#8211;<\/td>\n<\/tr>\n<tr style=\"height: 18px\">\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">B<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">2<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-S<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">0<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">&#8211;<\/td>\n<\/tr>\n<tr style=\"height: 18px\">\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">C<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">2<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-S<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">0<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">A<\/td>\n<\/tr>\n<tr style=\"height: 18px\">\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">D<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">4<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">S-S<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">0<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">A<\/td>\n<\/tr>\n<tr style=\"height: 18px\">\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">E<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">1<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-S<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">0<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">B<\/td>\n<\/tr>\n<tr style=\"height: 18px\">\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">F<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">2<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-S<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">0<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">C, D<\/td>\n<\/tr>\n<tr style=\"height: 18px\">\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">G<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">3<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-S<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">0<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">E<\/td>\n<\/tr>\n<tr style=\"height: 18px\">\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">H<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">1<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-S<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">2 weeks<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">G<\/td>\n<\/tr>\n<tr style=\"height: 18px\">\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">I<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">4<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-S<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">0<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">G<\/td>\n<\/tr>\n<tr style=\"height: 18px\">\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 84.2656px\">J<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 159.5px\">1<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 177.547px\">F-F<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 185.562px\">-1 week<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 18px;width: 181.656px\">F<\/td>\n<\/tr>\n<tr style=\"height: 50px\">\n<td style=\"text-align: center;vertical-align: middle;height: 50px;width: 84.2656px\">K<\/td>\n<td style=\"height: 50px;width: 159.5px;text-align: center;vertical-align: middle\">3<\/td>\n<td style=\"height: 50px;width: 177.547px\">\n<p class=\"indent\">\u00a0 \u00a0 \u00a0 \u00a0F-S for H<\/p>\n<p class=\"indent\">\u00a0 \u00a0 \u00a0 \u00a0S-F for J<\/p>\n<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 50px;width: 185.562px\">5 days for J<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 50px;width: 181.656px\">J, H<\/td>\n<\/tr>\n<tr style=\"height: 17px\">\n<td style=\"text-align: center;vertical-align: middle;height: 17px;width: 84.2656px\">L<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 17px;width: 159.5px\">4<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 17px;width: 177.547px\">F-S<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 17px;width: 185.562px\">0<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 17px;width: 181.656px\">I<\/td>\n<\/tr>\n<tr style=\"height: 59px\">\n<td style=\"text-align: center;vertical-align: middle;height: 59px;width: 84.2656px\">M<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 59px;width: 159.5px\">1<\/td>\n<td style=\"height: 59px;width: 177.547px\">\n<p class=\"indent\">\u00a0 \u00a0 \u00a0 \u00a0F-S for K<\/p>\n<p class=\"indent\">\u00a0 \u00a0 \u00a0 \u00a0F-F for L<\/p>\n<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 59px;width: 185.562px\">1 week for L<\/td>\n<td style=\"text-align: center;vertical-align: middle;height: 59px;width: 181.656px\">K, L<\/td>\n<\/tr>\n<\/tbody>\n<\/table>\n<p style=\"text-align: left\">When we start a new project on Microsoft Project, checking \u201cProject Summary Task\u201d under the \u201cFormat\u201d tab is useful. MS Project gives the row number zero to the project summary task. The question mark at the end of the duration shows that the duration is estimated (Figure 7.6.1).<\/p>\n<figure id=\"attachment_223\" aria-describedby=\"caption-attachment-223\" style=\"width: 624px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2022\/03\/Figure-7.20.jpg\" alt=\"Project Summary Task row on Microsoft Project\" width=\"624\" height=\"59\" class=\"wp-image-210 size-full\" srcset=\"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2022\/03\/Figure-7.20.jpg 624w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2022\/03\/Figure-7.20-300x28.jpg 300w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2022\/03\/Figure-7.20-65x6.jpg 65w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2022\/03\/Figure-7.20-225x21.jpg 225w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2022\/03\/Figure-7.20-350x33.jpg 350w\" sizes=\"auto, (max-width: 624px) 100vw, 624px\" \/><figcaption id=\"caption-attachment-223\" class=\"wp-caption-text\"><strong>Figure 7.6.1: Project Summary Task<\/strong><\/figcaption><\/figure>\n<p>Besides, just in the very beginning, it is of high importance to check \u201cCritical Tasks\u201d and \u201cSlack\u201d under the \u201cFormat\u201d tab (Figure 7.6.2). When we type the tasks (activities), the Gantt Chart will highlight the critical tasks in red and the non-critical tasks in blue.<\/p>\n<figure id=\"attachment_223\" aria-describedby=\"caption-attachment-223\" style=\"width: 594px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.21.jpg\" alt=\"Critical tasks and slack options are checked on Microsoft Project\" width=\"594\" height=\"144\" class=\"wp-image-211 size-full\" srcset=\"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.21.jpg 594w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.21-300x73.jpg 300w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.21-65x16.jpg 65w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.21-225x55.jpg 225w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.21-350x85.jpg 350w\" sizes=\"auto, (max-width: 594px) 100vw, 594px\" \/><figcaption id=\"caption-attachment-223\" class=\"wp-caption-text\"><strong>Figure 7.6.2: Checked critical tasks and slack under the Format tab<\/strong><\/figcaption><\/figure>\n<p>As the durations are in weeks, we should change the settings in the Options under the \u201cFile\u201d tab. \u201cDuration is entered in\u201d is changed to \u201cWeeks\u201d (Figure 7.6.3).<\/p>\n<figure id=\"attachment_223\" aria-describedby=\"caption-attachment-223\" style=\"width: 626px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.22.jpg\" alt=\"Changing the duration unit in Project Options box on Microsoft Project\" width=\"626\" height=\"260\" class=\"wp-image-212 size-full\" srcset=\"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.22.jpg 626w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.22-300x125.jpg 300w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.22-65x27.jpg 65w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.22-225x93.jpg 225w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.22-350x145.jpg 350w\" sizes=\"auto, (max-width: 626px) 100vw, 626px\" \/><figcaption id=\"caption-attachment-223\" class=\"wp-caption-text\"><strong>Figure 7.6.3: Changing the duration unit<\/strong><\/figcaption><\/figure>\n<p>First, we should type each activity in the \u201cTask Name\u201d column and durations in the \u201cDuration\u201d column. Then, we can select the predecessors from the dropdown menu in the \u201cPredecessors\u201d column (Figure 7.6.4).<\/p>\n<figure id=\"attachment_223\" aria-describedby=\"caption-attachment-223\" style=\"width: 468px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.23.jpg\" alt=\"Selecting predecessor A by clicking on A on the dropdown menu\" width=\"468\" height=\"342\" class=\"wp-image-213 size-full\" srcset=\"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.23.jpg 468w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.23-300x219.jpg 300w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.23-65x48.jpg 65w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.23-225x164.jpg 225w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.23-350x256.jpg 350w\" sizes=\"auto, (max-width: 468px) 100vw, 468px\" \/><figcaption id=\"caption-attachment-223\" class=\"wp-caption-text\"><strong>Figure 7.6.4: Selecting predecessors from the dropdown menu<\/strong><\/figcaption><\/figure>\n<p>When we finish typing all the activity predecessors, the Gantt Chart will be completed on the right side of the window (Figure 7.6.5). As indicated above, red bars show critical tasks (with zero slack) and non-critical tasks (with slacks). MS Project allows the users to change the colors of the bars.<\/p>\n<figure id=\"attachment_223\" aria-describedby=\"caption-attachment-223\" style=\"width: 626px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.24.jpg\" alt=\"Gantt chart with red bars showing critical tasks (with zero slack) and non-critical tasks (with slacks).\" width=\"626\" height=\"161\" class=\"wp-image-214 size-full\" srcset=\"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.24.jpg 626w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.24-300x77.jpg 300w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.24-65x17.jpg 65w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.24-225x58.jpg 225w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.24-350x90.jpg 350w\" sizes=\"auto, (max-width: 626px) 100vw, 626px\" \/><figcaption id=\"caption-attachment-223\" class=\"wp-caption-text\"><strong>Figure 7.6.5: Gantt Chart<\/strong><\/figcaption><\/figure>\n<p>For this exercise, we are not changing the \u201cTask Mode,\u201d which is either automatically scheduled or manually scheduled (Figure 7.6.6). Project summary tasks are automatically scheduled since they adjust the duration and start and finish dates automatically when activity durations and predecessors are typed.<\/p>\n<figure id=\"attachment_223\" aria-describedby=\"caption-attachment-223\" style=\"width: 226px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.25.jpg\" alt=\"Task mode dropdown menu showing Manually Scheduled and Auto Scheduled on Microsoft Project\" width=\"226\" height=\"253\" class=\"wp-image-215 size-full\" srcset=\"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.25.jpg 226w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.25-65x73.jpg 65w\" sizes=\"auto, (max-width: 226px) 100vw, 226px\" \/><figcaption id=\"caption-attachment-223\" class=\"wp-caption-text\"><strong>Figure 7.6.6: Task mode<\/strong><\/figcaption><\/figure>\n<p>When we double-click a task, the \u201cTask Information\u201d window opens (Figure 7.6.7). The dependency type is \u201cFinish-to-Start (FS)\u201d as default. Now we can change dependencies as indicated in Table 7.6.1.<\/p>\n<figure id=\"attachment_223\" aria-describedby=\"caption-attachment-223\" style=\"width: 975px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.26.jpg\" alt=\"Predecessor tab on task information window. The columns are ID, Task Name, Type, and Lag.\" width=\"975\" height=\"367\" class=\"wp-image-216 size-full\" srcset=\"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.26.jpg 975w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.26-300x113.jpg 300w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.26-768x289.jpg 768w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.26-65x24.jpg 65w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.26-225x85.jpg 225w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.26-350x132.jpg 350w\" sizes=\"auto, (max-width: 975px) 100vw, 975px\" \/><figcaption id=\"caption-attachment-223\" class=\"wp-caption-text\"><strong>Figure 7.6.7: Task Information window<\/strong><\/figcaption><\/figure>\n<p>When we are done with predecessor types (dependencies), the predecessors with dependencies different from FS will appear in the \u201cPredecessors\u201d column for the relevant activities (Figure 7.6.8). These dependencies are shown inside a red circle in Figure 7.6.8.<\/p>\n<figure id=\"attachment_223\" aria-describedby=\"caption-attachment-223\" style=\"width: 863px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.27.jpg\" alt=\"Predecessors and their dependencies on the Predecessors column on Microsoft Project\" width=\"863\" height=\"502\" class=\"wp-image-217 size-full\" srcset=\"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.27.jpg 863w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.27-300x175.jpg 300w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.27-768x447.jpg 768w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.27-65x38.jpg 65w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.27-225x131.jpg 225w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.27-350x204.jpg 350w\" sizes=\"auto, (max-width: 863px) 100vw, 863px\" \/><figcaption id=\"caption-attachment-223\" class=\"wp-caption-text\"><strong>Figure 7.6.8: Predecessors and dependencies<\/strong><\/figcaption><\/figure>\n<p>After we change the dependencies, clicking \u201cRespect Links\u201d under the \u201cTask\u201d tab is important since the task mode is manually scheduled, and the new dependencies may affect the precedence relationships. As shown in Figure 7.6.9, MS Project highlights the boxes in light blue if there is a change.<\/p>\n<figure id=\"attachment_223\" aria-describedby=\"caption-attachment-223\" style=\"width: 349px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.28.jpg\" alt=\"Microsoft Project highlights the changes in a light blue color.\" width=\"349\" height=\"260\" class=\"wp-image-218 size-full\" srcset=\"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.28.jpg 349w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.28-300x223.jpg 300w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.28-65x48.jpg 65w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.28-225x168.jpg 225w\" sizes=\"auto, (max-width: 349px) 100vw, 349px\" \/><figcaption id=\"caption-attachment-223\" class=\"wp-caption-text\"><strong>Figure 7.6.9: Highlighted changes<\/strong><\/figcaption><\/figure>\n<p>As shown in Figure 7.6.10, the dependency between A and D is not FS. It is Start-to-Start (SS). Therefore, the arrow starts from the left side of A\u2019s bar on the Gantt Chart and connects to the left side of D\u2019s bar. When it is FS, the arrow starts from the right side of the predecessor and connects to the left side of the successor, as can be seen in Figure 7.6.10 between A and C.<\/p>\n<p>&nbsp;<\/p>\n<figure id=\"attachment_223\" aria-describedby=\"caption-attachment-223\" style=\"width: 523px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.29.jpg\" alt=\"Start-to-Start dependency between two activities\" width=\"523\" height=\"294\" class=\"wp-image-219 size-full\" srcset=\"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.29.jpg 523w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.29-300x169.jpg 300w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.29-65x37.jpg 65w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.29-225x126.jpg 225w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.29-350x197.jpg 350w\" sizes=\"auto, (max-width: 523px) 100vw, 523px\" \/><figcaption id=\"caption-attachment-223\" class=\"wp-caption-text\"><strong>Figure 7.6.10: Start-to-Start dependency<\/strong><\/figcaption><\/figure>\n<p>To see the slacks for each activity, we can add a new column named \u201cFree Slack\u201d (Figure 7.6.11). The black underline attached to the left of Activity C in the Gantt Chart also shows the slack (Figure 7.6.10).<\/p>\n<figure id=\"attachment_223\" aria-describedby=\"caption-attachment-223\" style=\"width: 371px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.30.jpg\" alt=\"Free slack column on Microsoft Project\" width=\"371\" height=\"249\" class=\"wp-image-220 size-full\" srcset=\"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.30.jpg 371w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.30-300x201.jpg 300w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.30-65x44.jpg 65w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.30-225x151.jpg 225w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.30-350x235.jpg 350w\" sizes=\"auto, (max-width: 371px) 100vw, 371px\" \/><figcaption id=\"caption-attachment-223\" class=\"wp-caption-text\"><strong>Figure 7.6.11: Free Slack column<\/strong><\/figcaption><\/figure>\n<p>Now we can create an activity network diagram by selecting \u201cNetwork Diagram\u201d on the dropdown menu that appears when we click the Gantt Chart located on the far-left part of the \u201cTask\u201d tab (Figure 7.6.12).<\/p>\n<figure id=\"attachment_223\" aria-describedby=\"caption-attachment-223\" style=\"width: 222px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.31.jpg\" alt=\"Selecting network diagram from the dropdown menu under Gantt Chart icon\" width=\"222\" height=\"271\" class=\"wp-image-221 size-full\" srcset=\"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.31.jpg 222w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.31-65x79.jpg 65w\" sizes=\"auto, (max-width: 222px) 100vw, 222px\" \/><figcaption id=\"caption-attachment-223\" class=\"wp-caption-text\"><strong>Figure 7.6.12: Selecting network diagram<\/strong><\/figcaption><\/figure>\n<p>Figure 7.6.13 displays the network diagram in a non-collapsed format. We should scroll toward the right to see other activities.<\/p>\n<figure id=\"attachment_223\" aria-describedby=\"caption-attachment-223\" style=\"width: 624px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.32.jpg\" alt=\"Network diagram when it is not collapsed\" width=\"624\" height=\"144\" class=\"wp-image-222 size-full\" srcset=\"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.32.jpg 624w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.32-300x69.jpg 300w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.32-65x15.jpg 65w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.32-225x52.jpg 225w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.32-350x81.jpg 350w\" sizes=\"auto, (max-width: 624px) 100vw, 624px\" \/><figcaption id=\"caption-attachment-223\" class=\"wp-caption-text\"><strong>Figure 7.6.13: Network Diagram (Not collapsed)<\/strong><\/figcaption><\/figure>\n<p>To see the whole diagram without details, we should click \u201cCollapse Boxes\u201d and check \u201cStraight Links\u201d under the \u201cNetwork Diagram Tools \u2013 Format\u201d tab (Figure 7.6.14). The network diagram in MS Project illustrates the links in FS dependency. Therefore, seeing other dependencies on the Gantt Chart view is convenient.<\/p>\n<figure id=\"attachment_223\" aria-describedby=\"caption-attachment-223\" style=\"width: 467px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/pressbooks.ulib.csuohio.edu\/project-management-navigating-the-complexity\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.33.jpg\" alt=\"Network diagram when all the labels on the nodes are removed.\" width=\"467\" height=\"219\" class=\"wp-image-223 size-full\" srcset=\"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.33.jpg 467w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.33-300x141.jpg 300w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.33-65x30.jpg 65w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.33-225x106.jpg 225w, https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-content\/uploads\/sites\/183\/2024\/07\/Figure-7.33-350x164.jpg 350w\" sizes=\"auto, (max-width: 467px) 100vw, 467px\" \/><figcaption id=\"caption-attachment-223\" class=\"wp-caption-text\"><strong>Figure 7.6.14: Network diagram (Collapsed)<\/strong><\/figcaption><\/figure>\n","protected":false},"author":3,"menu_order":7,"template":"","meta":{"pb_show_title":"on","pb_short_title":"","pb_subtitle":"","pb_authors":[],"pb_section_license":""},"chapter-type":[],"contributor":[],"license":[],"class_list":["post-224","chapter","type-chapter","status-publish","hentry"],"part":175,"_links":{"self":[{"href":"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-json\/pressbooks\/v2\/chapters\/224","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-json\/pressbooks\/v2\/chapters"}],"about":[{"href":"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-json\/wp\/v2\/types\/chapter"}],"author":[{"embeddable":true,"href":"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-json\/wp\/v2\/users\/3"}],"version-history":[{"count":4,"href":"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-json\/pressbooks\/v2\/chapters\/224\/revisions"}],"predecessor-version":[{"id":829,"href":"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-json\/pressbooks\/v2\/chapters\/224\/revisions\/829"}],"part":[{"href":"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-json\/pressbooks\/v2\/parts\/175"}],"metadata":[{"href":"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-json\/pressbooks\/v2\/chapters\/224\/metadata\/"}],"wp:attachment":[{"href":"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-json\/wp\/v2\/media?parent=224"}],"wp:term":[{"taxonomy":"chapter-type","embeddable":true,"href":"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-json\/pressbooks\/v2\/chapter-type?post=224"},{"taxonomy":"contributor","embeddable":true,"href":"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-json\/wp\/v2\/contributor?post=224"},{"taxonomy":"license","embeddable":true,"href":"https:\/\/pressbooks.ulib.csuohio.edu\/projectmanagement2ndedition\/wp-json\/wp\/v2\/license?post=224"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}