Chapter 6. Communication Management, Leadership, and Project Team Management

6.3 Communications Management Protocol

The communication management plan can include a protocol that delineates all the critical communication channels for the team and stakeholders, such as the purpose of communication, frequency of communications, ICTs utilized, types of information to be communicated, and participants. Table 6.3.1 provides an example of a Communications Management Protocol for Grocery LLC’s Mobile Commerce Project (see 1.2).

Table 6.3.1. Communications Management Protocol for Grocery LLC’s Mobil Commerce Project
Purpose of Communication Schedule Frequency ICTs or Other Means Utilized Types of Information Participants: Team Members and Stakeholders
Planning Every Monday at 10:00 am Microsoft Teams, Zoom, OneDrive, Emails Requirements, project activities, updated schedules, cost estimates, risks, and issues All team members, Project Manager, IT Department, Business Analysts, Store Managers
Stakeholder Requirements Gathering Weekly, Tuesday-Friday between May 2 – June 10, 2022 Zoom, Online Surveys, Emails, Phone Calls Customer needs, expectations, product preferences, operational constraints, technical needs Store Managers, Employees, Customers, Project Team, Business Analysts
Design Review Bi-weekly, every 2nd and 4th Wednesday of the month Microsoft Teams, Zoom, OneDrive, Emails Mobile app wireframes, website designs, feedback on UI/UX, functional requirements Project Manager, IT Development Team, UI/UX Designers, Marketing Team, Store Managers
Retrospective Every Friday at 4:00 PM Microsoft Teams, Zoom, OneDrive, Emails Status updates, lessons learned, challenges faced during the week, successes All team members, Project Manager
Status Updates Every Monday after planning meetings or as needed Emails, Zoom, OneDrive Progress reports, tracking Gantt charts, budget and schedule comparisons, risk assessments Project Sponsor, Clients, Store Managers, Project Manager, Business Analysts
Client Progress Review Monthly, the last Monday of the month Zoom, Emails, OneDrive High-level progress summary, key milestones achieved, risks, issues, financial overview Clients, Project Sponsor, Project Manager, Marketing Department
Digital Marketing Coordination Monthly, the last Friday of the month Zoom, Emails, Collaboration tools (Trello, Slack) Digital marketing campaign progress, mobile app and website launch plan, customer engagement strategy Marketing Team, IT Team, Business Analysts, Project Manager, Store Managers
Final Project Review October 20, 2022 Zoom, Microsoft Teams, In-person (if safe) Final deliverables, lessons learned, user acceptance testing results, next steps for post-launch phase Project Manager, All Team Members, Store Managers, IT Department, Clients