Chapter 4. Project Planning and the Project Scope

4.5 Microsoft Project Tutorial

Microsoft Project is one of the most common software tools in project management worldwide. In this book, we use Project Professional 2019. The tutorials in this book apply to all the recent versions of Microsoft Project.

When you open MS Project for the first time, you can open a “Blank Project” or select a template (Figure 4.5.1).

Figure 4.3: MS Project “New” Window
Figure 4.5.1: MS Project “New” Window

When you select “Blank Project,” the project page will open with a ribbon that includes tabs (in the same format we have on Microsoft Office programs such as Word, Excel, and PowerPoint) (Figure 4.5.2). While the default view is “Gantt with Timeline,” we changed it from “Options” to “Gantt Chart” view. Therefore, Figure 4.4 doesn’t display the timeline. In Figure 4.5.3, under Project View, the default view is set as Gantt with Timeline.

Figure 4.4: Blank Project (Gantt Chart with Timeline)
Figure 4.5.2: Blank Project (Gantt Chart with Timeline)

 

Figure 4.5: Project Options – General tab
Figure 4.5.3: Project Options – General tab

We will use “Gantt with Timeline” as our default view in this chapter’s tutorial and the following chapters. Besides, we are not changing the schedule options. This means we are not working on the weekends, and our durations are automatically labeled “days.” However, we can type another unit such as a week (wk or wks) or month (mon or mons) (Figure 4.5.4).

Figure 4.6: Project Options – Schedule tab
Figure 4.5.4: Project Options – Schedule tab

Under the “Format” tab, we should check “Project Summary Task” first. Therefore, the total duration of our project can be automatically calculated by MS Project. The row number becomes zero for the project summary task (Figure 4.5.5). If we insert a column titled “WBS,” the system also gives zero to this task. MS Project doesn’t use the name “Activity” but “Task.”

Figure 4.7: Project Summary Task
Figure 4.5.5: Project Summary Task

For this MS Project tutorial, we will use letters and numbers for the activities. A is the project, and the highest level is 1. The lowest level in our WBS is the third level (Table 4.5.1).

Table 4.5.1: Activities
WBS Level Activity 
1 A
2 a1
2 a2
3 a21
3 a22
1 B
2 b1
3 b11
3 b12
1 b2

After we type all the activities, we can select a1 and a2, and indent them as both are under A (Figure 4.5.6). WBS numbers are given automatically by MS Project when we indent and outdent. After we indent a1 and a2, these two activities can be subtasks of A, which could be considered a phase or major deliverable.

Figure 4.8: Indenting tasks “a1” and “a2”
Figure 4.5.6: Indenting tasks “a1” and “a2”

For a21 and a22 at the third level, we should click the “Indent Task” icon twice, as they are under a2 at the second level. Figure 4.5.7 displays the WBS numbers after all the activities have been indented.

Figure 4.9: Indenting all the tasks at second and third WBS levels
Figure 4.5.7: Indenting all the tasks at the second and third WBS levels

As can be seen in Figure 4.5.7, WBS numbers changed automatically when we indented the tasks. This tutorial served as an introduction to Microsoft Project and only discussed how a WBS can be created. Therefore, we have not typed the durations and predecessors. We will cover them in Chapter 7, “Scheduling”.

License

Icon for the Creative Commons Attribution-NonCommercial 4.0 International License

Project Management, 2nd Edition by Abdullah Oguz, Ph.D., PMP® is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License, except where otherwise noted.

Share This Book