Chapter 11. Monitoring and Controlling

11.5 MS Project Tutorial

This MS Project tutorial will elaborate on how to conduct an EVM analysis. Table 11.6 provides a project with 15 activities.

Table 11.6: Project Activities

Activity Duration (weeks) Predecessors
A 2
B 3
C 1 A, B
D 3 C
E 2 C
F 2 D, E
G 3 E
H 4 F, G
I 2 H
J 6 I
K 4 J
L 3 J
M 2 J
N 2 K, L, M
O 1 N

 

The Microsoft Project screenshot showing all the project activities, the schedule, and the Gantt Chart
Figure 11.2: WBS, Schedule, and the Gantt Chart

In this project, the resources that are assigned to each activity are given in Table 11.7. All the resources are “Work” type resources which means that they are either people or equipment.

Table 11.7: Resources and Costs

Resource Name Standard Rate Activities 
a $20.00/hr A
b $40.00/hr B
c $30.00/hr C
d $15.00/hr D
e $35.00/hr E
f $50.00/hr F
g $30.00/hr G
h $25.00/hr H
i $40.00/hr I
j $40.00/hr J
k $25.00/hr K
l $25.00/hr L
m $20.00/hr M
n $35.00/hr N
o $50.00/hr O
Additional Cost 1 $35.00/hr C
Additional Cost 2 $25.00/hr F

Under the View tab, we click the “Resource Sheet”. Then, we can type the resource names and costs as seen in Table 11.7. The Resource Sheet on MS Project is given in Figure 11.3.

Resource sheet including two additional costs
Figure 11.3: Resource Sheet

Let’s select all the resources except additional costs from the drop-down menu for each resource on the Gantt Chart view. Besides, we add a new column “Cost” to the left of “Resource Names”. As can be seen in Figure 11.4, the total estimated cost of the project is $52,400. This figure would be also our BAC (Budget at Completion).

 

Microsoft Project screenshot showing the activity list with the resources assigned to each activity
Figure 11.4: Gantt Chart View with the Resources Selected

Under the “Task” tab, we can select “Tracking Gantt” from the drop-down menu (Figure 11.5).

 

Selecting the Tracking Gantt view from the dropdown menu when clicked on the Gantt Chart icon on Microsoft Project
Figure 11.5: Selecting Tracking Gantt View

In order to create schedule and cost baselines, we must create a baseline by clicking “Set Baseline” under the “Project” tab. We can click OK as shown in Figure 11.6.

 

Microsoft Project screenshot showing the "Set Baseline" window
Figure 11.6: Set Baseline Window

The Tracking Gantt Chart is shown in Figure 11.7. As we haven’t indicated any progress yet, all the progress percentages are zero percent. Each bar is now composed of two horizontal parts. The lower part which is darker displays the baseline.

Bars showing the project activities on the Gantt Chart. The baseline is the bottom half of each bar highlighted with dark gray.
Figure 11.7: Tracking Gantt Chart

The project started on June 6, 2022. The estimated completion date is December 30, 2022. Let’s assume that some time passed in the project. Let’s make the current date September 18, 2022. Under the “Project” tab, click “Project Information”. Changing the current date won’t suffice (Figure 11.8). It will help us to see the date on the Gantt Chart. Rather, we need to change the status date to create a scenario as of September 18, 2022.

Microsoft Project screenshot showing the Project Information Window (start date, current date, status date)
Figure 11.8: Project Information Window

Now, we can change the completion percentages for each activity, and add “Additional Resources” to create the impression as if we made some progress on activities, and spent more money on some of the activities. As indicated in Table 11.7, additional costs are added to activities C and F (Figure 11.9). The project cost changed to $55,800 with the additional costs from its cost baseline of $52,400.

 

Microsoft Project screenshot showing the situation after additional costs were added to the resources.
Figure 11.9: Additional Costs added to activities C and F

As shown in Table 11.8, we will also change the completion percentages for each activity.

Table 11.8: Completion Percentages for the Activities

Activity Completion Percentage
A 100
B 100
C 100
D 100
E 100
F 100
G 100
H 50
I 0
J 0
K 0
L 0
M 0
N 0
O 0

We can use the shortcuts for completion percentages (0%, 25%, 50%, 75%, 100%). Or double-clicking a task opens the “Task Information” window. From the “Percent complete” on this window, we can type any percentage (Figure 11.10).

Shortcuts for project completion percentages under the Task tab on Microsoft Project. The percentages are zero, 25, 50, 75, and 100.Figure 11.10: Shortcuts for Completion Percentages

After we mark the completion percentages for each task, we can see the percentages to the left of each bar on the Gantt Chart (Figure 11.11). Besides, the upper horizontal section of each bar will get darker for 100% completion, and the “Indicators” column will place ticks for these activities. Activity H has a 50% completion. Therefore, its upper horizontal section turned darker red for half of the activity. We should remember that weekends are considered holidays on Microsoft Project (default setting). Therefore, the coverage area may not necessarily display a 50% area on a bar.

Microsoft Project screenshot showing the completion percentages on the Gantt Chart next to each bar representing activities
Figure 11.11: The Percentages marked to the right of each bar on the Gantt Chart

So, our scenario dictates that we finished 100% of activities A, B, C, D, E, F, and G, and 50% of activity H. Besides, we spent more money on activities C and F.

Now, we can open the EVM table. In the View tab, we click Tables and select More Tables. In the new menu window, we choose Earned Value. In the new sheet, we should insert SPI as a new column to the right of the existing “SV” column, and CPI as a new column to the right of the existing “CV” column. Figure 11.12 displays the Earned Value table view as of September 18, 2022. An SPI value of 0.92 indicates that our project is behind schedule. A CPI value of 0.88 indicates that our project has an overrun budget issue. Microsoft Project provides EAC, BAC, and VAC values (Figure 11.12). Our cost baseline was $52,400. If we assume that the CPI value of 0.88 doesn’t change during the rest of the project, we can estimate to pay $59,761 (EAC – Estimate at Completion) by the end of the project, which is $7,361 (VAC – Variation at Completion) more than our cost baseline.

Earned value table view on Microsoft Project. The columns are Planned Value, Earned Value, AC, SV, SPI, CV, CPI, EAC, BAC, and VAC.
Figure 11.12: Earned Value Table View

Our schedule baseline was 30 weeks (Figure 11.2). SPI is 0.92 as of September 18, 2022. If we cannot improve this SPI and it remains the same during the rest of the project, there may be a delay of 2.6 weeks [1 – (30 weeks / 0.92)].

License

Icon for the Creative Commons Attribution-NonCommercial 4.0 International License

Project Management by Abdullah Oguz is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License, except where otherwise noted.

Share This Book